Last week I said I would:
  1. Help with the Sametime 8.5.1 project - especially with Linux client testing (done, but ongoing)
  2. Blog internally about experiences using Sametime AV technologies for the  All Hands meeting (done)
  3. Decide next steps with the IBM 2.0 book project (done - will formally communicate this next week)
  4. Continue the salary review process (first pass done - second pass due next week)
  5. Continue the 2010 promotion review process for the more senior bands (ongoing)

Next Week I will do the following actions:
  1. Help with the Sametime 8.5.1 project - especially with Linux client testing
  2. Help Gabriela draft the paper for the Blogtalk conference
  3. Communicate decision on the IBM 2.0 book to those involved
  4. Do second pass of the salary review plan
  5. Continuethe 2010 promotion review process for the more senior bands.